Restoration of Whimbrel 1999
January
l999Week l at Penpol-
trial fitting of stern post/aft D-W successful -good news indeed. Whimbrel rebuild has
now started!

February: week2 in Penpol- more
new faces in boatyard -Henry -time served shipwright very knowledgeable/
helpful. Original keelson dropped out after all remaining frames cut through (+
extra props in place) Hardboard patterns made for upper & lower sections of
keelson. Whimbrel now spineless but looks better
without old keelson.
March l999 -20cu.ft oak delivery from Whippletree
- 211 +311 planks for hog,fore
D-W and 160 of 211 x 1/211 strips for frame laminations (total £820). Hog
assembled from 2 + 311 planks:nice
but 311 short! Fore D-W rebuilt -811 wide,611 deep and
61 long (triangle). 1 pair of 311 by 121 by 1811 wide oak planks (8cu. ft) purchased
for new keelson: very heavy indeed -long suffering trailer. Eventually rough
cut on massive bandsaw with moving table at nearby ex-
chicken farm but still needing much finishing with electric planer for bevels.

April 1999- Trailer fully loaded for

May
l999 - week3 at Penpol (postponed by 7 days-lack of enthusiasm!) Cheek patterns confirmed correct shape of new
frames -each glued to 1.511 overall thickness.
Unsuccessful screw fastening -revert to copper nail riveting -(much
better and rapid with Henry's assistance but noisy. Eight frames - S/B nos:13 ~20 replaced and rivetted up. Looking good. Fell off ladder -hard landing on ground -no
broken bones- but painkillers for 7days! Ladder top now fastened securely to
sheer plank. Patterns taken for alternate port frames 13-20. -'bad
news' bill from boatyard - overcharged for yard use and Henry's
labour-challenged successfully. 'Windmill' yard very pleasant location for
stage 2 rebuild - Kevin/Kevin most agreeable -reasonable charge. No need to
expedite removal from Penpol unless further Isurchargingl.Quotations for transport from £530 ~800 +
cranes £150 x2
June l999- fast production line build of port frames 13-20 +
S/B 12 + 20. Overproduction resulted in twin P14 x 2 and P21 x2! Steam-bend-glue-clamp-clean up-restart again-13 in all. Time
to spare- bowsprit started and nearly completed.
July 1999-week4 -joined by David Groom (Gadebury
care manager) -tremendous worker -really excellent with cutting out recesses
for frame ends. Replaced on Friday by Dave Clout (trust me I'm a welder)- also a demon worker. 11 frames replaced, new fore
deadwood (mast support) and aft end of lower bow stem timber made good by top
and starboard infills (Dave G). Weather very hot
-work hard going. A real step forward indeed! Trev. taken
to hospital with chest pain ?cause. Thorough tidy up - templates for frames
22-25 made. Frames 22-25 (twinned) + S/B 12 made up. Order placed for larch
planking + pitch pine for stringers -Traditional sail (Salcombe)
Aug 1999 -overnight trip in Grahams tired VW transporter to collect 10cwt load of seasoned
]arch for planking. Successful trip not with -standing
numerous mechanical challenges-warning lights/buzzers alarms ete -exhausting but worth it. Plenty of wood for
lower planks both sides + spare. Week5- alone in B&B
-planking fraught with bevel type problems (steep learning curve). New
planks look good. Four more frames replaced. Week spoilt by silly mistakes!
Welcome help from Jamie.

Sept 1999 - spoilt frames (from week5) made good. Port side
lower planks roughed out. Arrival of Whimbrel -(sans ballast keel/rudder) -brought by Brian Pope on boat
trailer. Hair raising lift off by mobile crane -disaster narrowly averted due
to boat rotating inside strops (due to inadvisable climbing inside boat). Boat
eventually secured safely on ground at Great Revel End Farm -still looking
rather sorry for herself -reframing continues from 25
onwards -both sides. Propellor shaft removed.

Oct 1999 -Plugging time! Plank damage from old fastenings
made good by internal 3/811 oak parallel plug
followed by 1/2" cone shaped external redwood plug. Time
consuming but effective. 40' elderly portcabin
purchased (£560) for workshop +rest room -off loaded in wrong location but too
heavy to move ourselves -external/internal window shutters fitted,security
and power laid on - impressive premises !
Double curved frames with complex bevels
fitted around rudder post -the ultimate test in frame fitting. Few stern frames
salvaged including solid frame for main sheet horse. Several frames secured by
screws instead -less satisfactory than rivetting. The
transom does not look quite so good -will need further attention
November 1999 -

Portacabin moved by 'Groundforce'
(farmer & crew) into correct site using tractor + trailer and crane
combination. Tremendous achievement -pity about the cracks in the roof! Weather
still holding fair. Stern frames finished at last-time to move forward. Old
paint stripped off starboard side -long slow job with making good all plug
holes -followed by grey primer below waterline and white above. Starboard sheer
& 4th + 3rd planks fitted -great improvement.
December 1999

Wrought iron keel bolt forged by Welder Dave into mushroom ends -using
farmer Paul's forge -not a success! Lifting frame with detachable legs
constructed by Welder Dave -very heavy (l ton) and robust -excellent design but
costly at £1000. Mobile crane -manned by father & son:
Dave lift 3.25ton cast iron ballast keel on to lifting frame with legs fitted.

![]()
Return to Main index - Onto the next Diary
Page