Phase 1: Penpol boatyard (Cornwall) :Nov'98
Replace stern post, Replace keelson and hog + metal floor hangers Replace aft and fore deadwoods midship reframing F 12-22: both sides fit new planking lower four -port side
Phase 2: Relocate to Hemel Hempstead (Herts) -Sept l999
Set up portacabin workshop. Complete reframing stern & bow sections. Fit ballast keel and keel bolts. Replace four lowest planks: starboard. -Prepare starboard side for undercoating. -Construct 'winter' roof over boat.
Xmas & New Millennium
progress so far
Phase 3:
Fit new sheer planks + beam shelves Fit deck beams & carlines. Fit hanging & lodging knees. Fit plywood decking. Construct fore hatch. Construct cabin roof Construct cockpit
Xmas 2000
Phase 4:
internal fitting out. fit 20 HP diesel engine order: spars, sails, rigging. contract out for teak laid deck caulk all seams. replace faulty keel bolts paint hull
Phase 5:
Transport to Ipswich :Fox's Marina Final preparations for launching.
|